PLC Project Process and Best Practices: From Requirements to Commissioning and Support

On this page

A PLC project turns a machine or process requirement into a tested, documented control system that operators can run and maintenance can support. The phases are similar whether the scope is a single packaging machine, a production line or a process skid. Most project trouble comes not from programming but from unclear requirements, late changes, incomplete testing and missing documentation, so this guide focuses on the deliverables and practices that prevent them.

PLC Project Process: Requirements, Design, Programming, Testing, Commissioning, Documentation
A structured process from requirements to documented handover.

For plant-wide and multi-site projects, see DCS Project Lifecycle and SCADA Project Process.

Phase 1: Requirements

  • Capture what the machine or process must do: products, speeds, modes (automatic, manual, maintenance), recipes, interfaces and operator tasks.
  • Agree the standards to follow: customer automation standards, preferred PLC platform, naming conventions, HMI style, network and security rules.
  • Identify interfaces to upstream and downstream machines, MES or SCADA.

Deliverable: user requirements specification (URS).

Phase 2: Risk assessment and safety

For machinery, a risk assessment (ISO 12100 gives the general principles) identifies hazards and required risk reduction. Safety functions such as emergency stop, guard interlocking and safe speed are then specified with required performance levels (ISO 13849-1) or SIL (IEC 62061). In process skids, safety instrumented functions follow IEC 61511. In the EU, machinery must meet the Machinery Directive, which is being replaced by the Machinery Regulation (EU) 2023/1230, applicable from 20 January 2027.

Deliverables: risk assessment, safety requirements specification, safety function list. See PLC Industry Standards and Functional Safety.

Machine Safety in a PLC Project: Risk assessment, Safety functions, Design, Implement, Validate
Safety starts with the risk assessment, before hardware design.

Phase 3: Functional design

  • Functional design specification (FDS): sequences, modes, interlocks, alarms, recipes, HMI screens and communication, described so that the customer can approve them and the tester can test them.
  • I/O list: every signal with tag, description, type, range, module and channel.
  • Alarm list with priorities and operator responses.
  • Network architecture and IP addressing, including security zones. See OT Network Design Fundamentals.

Phase 4: Hardware and electrical design

  • Select the PLC platform, I/O and safety components with spare capacity for changes. See PLC Components and Types of PLCs.
  • Electrical schematics, panel layout, cable lists, power supply sizing, grounding and EMC design.
  • Panel standards such as IEC 60204-1 (electrical equipment of machines) and, where relevant, UL 508A in North America.

Phase 5: Programming and HMI

  • Program according to the agreed standard: structure by equipment, reusable function blocks, state machines for sequences. See PLC Programming Best Practices.
  • Build HMI screens from templates following the HMI style guide.
  • Keep a change log from the first day and archive versions.

Phase 6: Testing before site

Test What it covers
Internal test / simulation Logic tested against the FDS with simulated I/O or a machine model
Panel test Wiring, power, I/O channels, network communication
Factory acceptance test (FAT) Customer witnesses operation against the FDS: modes, sequences, interlocks, alarms, faults, recipes
Safety function validation Each safety function tested and documented

Test failure scenarios, not only the normal sequence: sensor failures, drive faults, communication loss, emergency stops and power return. See PLC Programming Software and Tools for simulation.

What to Test Before Site: Normal sequences, Sensor failures, Drive faults, Communication loss, Emergency stops, Power return
Test failure cases, not only the normal sequence.

Phase 7: Installation, SAT and commissioning

  1. Installation checks: mechanical, electrical, grounding, cable terminations.
  2. I/O checks: every input and output from device to PLC and HMI.
  3. Motor direction, drive parameters, valve operation.
  4. Functional tests with the machine dry, then with product.
  5. Site acceptance test (SAT) against agreed criteria.
  6. Performance run where the contract requires it.

Remove all forces and debug code before handover, and back up the final program.

Phase 8: Handover and support

Handover package:

  • As-built electrical drawings, I/O list and network documentation
  • Final PLC and HMI programs (archived, with version and change log)
  • FDS updated to match the final system
  • Safety validation records
  • Operating and maintenance manuals, spare parts list
  • Training records
  • Backup and restore procedure

After start-up: management of change, periodic backups and comparisons, firmware and security updates, and a lifecycle plan for obsolete components. See PLC Upgrading and Integration Challenges and PLC Security.

Best practices by phase

Phase Best practices
Requirements Get operators and maintenance involved early; agree standards before design
Safety Do the risk assessment before hardware design; specify safety functions with required PL or SIL
Design Write an FDS the customer can approve and the tester can test; freeze the I/O list with change control
Hardware Leave spare I/O, slots and power; separate field and CPU power supplies
Programming Use company standards and tested function blocks; review code
Testing Simulate before FAT; test fault paths; record every test result
Commissioning Check every I/O point; remove forces; back up the final program
Support Keep documents as-built; manage changes and backups; plan for obsolescence
Security Change default passwords, restrict remote access, harden engineering laptops

Common pitfalls

Pitfall Effect Prevention
Programming starts before the FDS is agreed Rework and disputes Approve the FDS first, or at least the typicals
Late I/O changes without control Wiring and program errors I/O freeze date and change control
FAT tests only the normal sequence Faults discovered on site Test plans that include failure cases
Site changes not reflected in documents Next change based on wrong drawings As-built updates as a handover condition
No backup of the final program Long recovery after a failure Archive at handover and after every change
Safety functions tested informally Unproven safety, legal risk Formal validation with records

Frequently asked questions

What are the main phases of a PLC project?

Requirements, risk assessment, functional design, hardware design, programming, testing (simulation and FAT), installation and commissioning with SAT, and handover with long-term support.

What documents are needed for a PLC project?

At minimum a requirements specification, risk assessment, functional design specification, I/O list, electrical drawings, network documentation, test records, final programs with change log, and operating and maintenance documentation.

What is the difference between FAT and SAT?

The factory acceptance test checks the system against the specification before shipment, often with simulated process conditions. The site acceptance test checks it on site with the real machine or process.

Key takeaways

  • Agree requirements, standards and the FDS before programming.
  • Do the risk assessment early and validate safety functions formally.
  • Simulate and test failure cases before FAT; check every I/O point on site.
  • Hand over as-built documents, archived programs and a support plan.

Before you apply this in a plant: this article is for education. Always check the current edition of the relevant standards, the manufacturer's documentation for your exact product and version, and your site's procedures. Safety-related work needs qualified personnel. See our editorial policy.

Written by Bhargava Reddy Kapireddy

Bhargava has 16 years of hands-on experience with MES, SCADA, DCS, PLC and industrial data systems across power generation, oil and gas, pharmaceuticals and process manufacturing. He founded MFG Tech Hub to share practical, vendor-neutral automation knowledge.

More about the author → How we write and review articles